Segment 3 N Roosevelt Avenue

10/10/2023 Roads have been paved. Pouring concrete driveways as the weather holds. Dirt work will begin week of October 16. 

9/26/2023 Curb and gutter is being poured along Roosevelt Avenue and 6th Street. 

8/23/2023 Starting Thursday 8/24, Rounds will begin building up the road in preparation to pave. Roosevelt Ave from NE 5th -7th and NE 6th from Prairie Ave to Roosevelt Ave will be closed to all traffic. Residents will need to move vehicles from these properties. Watch for notice from contractors for exact start date. 

8/2/2023 Contractor has completed watermain installation and will be working on services next. 

7/10/2023 - Road closures will begin Thursday morning July 13th along NE 6th Street and Roosevelt Ave 5th-7th. Dirt work and grinding of stumps will be worked on Monday-Wednesday. 

7/6/2023 - Prunty Construction is asking residents along NE 6th Street and Roosevelt between NE 5th Street and NE 7th Street for their cooperation to move any vehicles, trailers, campers, etc. from the streets prior to work commencing. It is anticipated that road closures will occur on July 10th but their subcontractor - Rounds Construction would like to begin some intermittent tree removal prior - potentially tomorrow Friday July 7th. When the Contractor begins surfacing removals on NE 6th Street it will be very difficult and in some cases impossible to move vehicles in and out particularly on the houses north of NE 6th Street without alley access. It is strongly advised that you move vehicles that you will need access to out of your driveways and garages prior to the work. The Contractor has been encouraged to keep a dialog with landowners along the project routes and Banner Associates and City staff will do the same, but please also feel free to initiate contact any of us regarding your questions and concerns. We thank you for your patience as we complete these necessary upgrade projects.

6/30/2023 - Letters were sent out to landowners out today regarding information for the project including the start date for the Contractor - Prunty Construction - of July 10th. They will begin with traffic control and erosion control measures, followed by removals. The phasing of the project has changed so please look at the updated map to the right for the updates. A Public Open House meeting has been scheduled for July 6th from 5:30 to 7:00 pm at the City Armory at 198 N. Van Eps Avenue. You are cordially invited to attend this Open House to put a face with the names of the people (City staff, Project Engineers, and Project Contractors) involved in the project, mingle, discuss your concerns, and have your questions answered. 

If you are unable to make the Open House meeting, you have not missed any sort of opportunity to ask questions or be provided with additional information. If you have any questions, please feel free to contact me by phone at (605) 256-7514 or email at ryan.hegg@cityofmadisonsd.com.

6/8/2023 - The project bids today! Once able, the City will share information on the contractor, dates for an Open House, and rough start dates for the project soon. Please check back as we will post information as it becomes available.

5/2/2023 Road construction project along N Roosevelt Avenue will be BID in May and work starting summertime 2023. Project will begin on NE 6th & NE 8th Streets.

roosevelt paving